Milton will begin its fall paving schedule beginning Monday, Sept. 27, said Carter Lucas, Milton's director of Public Works.
Lucas said three roads will be affected: Hickory Flat Road from the Fulton County line to Birmingham Highway (Ga. 372); Thompson Road from Hopewell Road to Tabbystone Place; and Morris Road from Webb to McGinnis Ferry roads.
Click here for a map of the areas affected. "Paving operations are expected to last approximately two weeks on each section depending on weather," said Lucas. "The project will begin on Hickory Flat, move to Thompson and finish on Morris."
The roads will remain open during the paving, but will be reduced to one travel lane. Motorists are encouraged to use alternate routes if possible during the construction period, he said.
"But if you must drive through the construction zone, use extreme caution and please drive slowly," said Lucas.
These portions of Morris, Thompson and Hickory Flat roads are ranked No. 2, 3 and 4, respectively, in the city's pavement management plan approved last year by City Council. The $1.121 million contract for the projects is to be carried out by Blount Construction Company.
Incorporated on December 1, 2006, the City of Milton is a distinctive community that embraces small-town life and heritage while preserving and enhancing the city's rural character. The City of Milton is committed to maintaining the unique quality of life for its constituents while efficiently delivering essential services to residents and businesses in an interactive community environment. For more information, visit
www.cityofmiltonga.us, or call 678-242-2500.
Labels: Milton City, Milton Georgia, paving